ARUA HOSPITAL ICU IS ABOUT ONE MONTH TO FINISH

The works at the Arua hospital intensive care unit are edging closer to finish

BY RICHARD DRASIMAKU & MUSINGUZI GOODLUCK

ARUA: 7th June, 2025

Engineers and Manson men at the construction site of the Intensive Care Unit at the Arua hospital are racing to against time to hit a one crucial target. Finishing and handing over of the facility for public use.

Arua Intensive Care unit is one month away from being handed over for public use

This follows month of a beehive of activity at the construction site as wheelbarrow pushers make their way with mixture of concrete up the rums for casting the concrete upstairs as plumbing technicians drill through to walls to fix pipes for the water, electricity and sewerage lines.

Engineers and casuals discussing their routine at the site

Scrubbing, screeding, floating and troweling works are all going simultaneously at the different rooms in the two-floor building.

The works launched at the beginning of 2024 ended the year at slightly above 70% according to the site manager, Allan Sitakange, of the HASO Engineers Company.

Leveling of the compound is on around the new ICU building

Company officials say what is being done now is final installation of electrical lines, gas and air-conditioning lines and the final painting, while outside the compound is being cleared of rubbish and debris.

ARUA ICU CONSTRUCTION HITS 71 PERCENT

West Nile December 30, 2024 BusinessCORONA NEWSFeaturedGovernanceHEALTHHealth NewsNationalNEWSNorthern RegionREGIONAL NEWSUncategorisedUncategorizedWest Nile Leave a comment 786 Views

The Arua hospital ICU complex

BY RICHARD DRASIMAKU AND GOODLUCK MUSINGUZI

ARUA: MONDAY, DECEMBER 30, 2024

There is a beehive of activity at the construction site for the Arua Hospital Intensive Care unit as wheelbarrow pushers make their way with mixture of concrete up the rums for casting the concrete upstairs as plumbing technicians drill through to walls to fix pipes for the water, electricity and sewerage lines.

Scrubbing, screeding, floating and troweling works are all going simultaneously at the different rooms in the two-floor building.

The works launched at the beginning of the year have hit 71% according to the site manager, Allan Sitakange, of the HASO Engineers Company.

Ongoing works inside the two storied ICU building in Arua

Arua ICU is a complex that will have a unit for the neonatal, life-saving support facilities, digital monitors, ventilators and high dependable beds for male and female patients, and isolation section for contagious diseases.

Sitakange said the works could have gone further than now but were delayed by the closure of the Karuma bridge which affected the transportation of construction materials.

Part of Arua hospital ICU being built with World Bank funding.jpg

With funding support from the World Bank under the Uganda Covid19 response and emergency preparedness project, the ministry of health has invested sh7.9 billion into the construction of the Arua regional referral hospital ICU.

It is one of the 14 projects at regional referral hospitals that the ministry undertook with funds that were initially meant for vaccine acquisition to fight Covid-19.

A Flourish chart

The new  facility will be a big leap in enhancing emergency medical care in the region, coming as a result of the lessons learnt from the Covid 19 pandemic.

At the time of the groundbreaking one year ago, the commissioner for infrastructure at the Ministry of Health, George Otim said the facility will help the people to receive specialized treatment that otherwise would have required an expensive referral to Mulago.

A section of the Arua hospital ICU under construction.jpg

In West Nile, the Arua facility adds to the sh1.9b ICU that was built at Adjumani hospital, funded under the Development Response to Displacement Impact program to cater for the emergency care needs of the population in the district where South Sudan refugees outnumber the locals.

About Kigezi News

Check Also

Issuance of Voter Location Slips (VLS) for General Elections 2026

By Musinguzi Goodluck In preparation for the General Elections 2026, the Electoral Commission has commenced …

Leave a Reply

Your email address will not be published. Required fields are marked *